Authority confronts 350 percent electrical cost spike on Rear Main North.
The Gardner Redevelopment Authority confronted a sharp cost overrun on its Rear Main Project North. National Grid increased its electrical estimate to $922,357.33 from an original $260,000, a 350 percent jump cited to supply-chain pressures and delayed approvals. Chair Tim Horrigan and members Jon